| Assessment Year | 1983 |
|---|---|
| Principal Product | STORAGE TANKS & FILTERS |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 2,000,000
lb
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $157,237 | 3,881,008 |
kWh
|
$0.041 |
| Natural Gas | $62,068 | 20,714 |
MMBtu
|
$3.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $50,474 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $50,474 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7312: Minimize use of outside make-up air for ventilation except when used for economizer cycle | $2,427 | $3,265 | - |
$2,427
-
MMBtu
|
|
| 02 | 2.7261: Install timers and/or thermostats | $26,153 | $3,160 | - |
$26,153
-
MMBtu
|
|
| 03 | 2.7261: Install timers and/or thermostats | $3,118 | $1,600 |
$3,118
107,562
kWh
|
- | |
| 04 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $1,097 | $200 |
$1,097
20,223
kWh
|
- | |
| 05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $323 | $730 | - |
$323
-
MMBtu
|
|
| 06 | 2.2223: Enhance sensitivity of temperature control and cutoff | $454 | $130 | - |
$454
-
MMBtu
|
|
| 07 | 2.7492: Use proper thickness of insulation on building envelope | $16,433 | $34,221 | - |
$16,433
-
MMBtu
|
|
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $469 | $127 |
$469
16,120
kWh
|
- | |
| TOTAL RECOMMENDED | $50,474 | $43,433 |
$4,684
143,905
kWh
|
$45,790
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $50,474 | $43,433 |
$4,684
143,905
kWh
|
$45,790
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs