ITAC Assessment: OK0081
ITAC logo
ITAC Assessment: OK0081
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product CERAMIC FIBER INSULATION
NAICS
n/a
SIC 3299: Nonmetallic Mineral Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 75
Plant Area
n/a
Annual Production 3,650,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $259,706 8,490,915
kWh
Natural Gas $5,311 1,702
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $4,112 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,518

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7226: Use computer programs to optimize hvac performance $681 $2,600 $681
33,118
kWh
-
02 2.7447: Install vinyl strip / high speed / air curtain doors $1,518 $1,800 - $1,518
-
MMBtu
03 2.7142: Utilize higher efficiency lamps and/or ballasts $476 $129 $476
9,965
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,437 $188 $1,437
50,410
kWh
-
TOTAL RECOMMENDED $4,112 $4,717 $2,594
93,493
kWh
$1,518
-
MMBtu
TOTAL IMPLEMENTED $1,518 $1,800 - $1,518
-
MMBtu
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs