ITAC Assessment: OK0077
ITAC logo
ITAC Assessment: OK0077
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1983
Principal Product REINFORCED PLASTIC PIPE
NAICS
n/a
SIC 3084: Plastics Pipe
Sales Range $10
M
to 50
M
# of Employees 170
Plant Area
n/a
Annual Production 0
units
Production Hrs. Annual 2,210
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $206,340 5,521,102
kWh
Natural Gas $229,760 74,970
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $81,572 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,584 $836 $1,584
35,756
kWh
-
02 2.7261: Install timers and/or thermostats $1,209 $2,125 - $1,209
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,825 $280 $4,825
175,264
kWh
-
04 2.7492: Use proper thickness of insulation on building envelope $11,300 $28,000 - $11,300
-
MMBtu
05 2.2122: Install / repair insulation on condensate lines $649 $388 - $649
-
MMBtu
06 2.2136: Install / repair insulation on steam lines $144 $160 - $144
-
MMBtu
07 2.2122: Install / repair insulation on condensate lines $281 $158 - $281
-
MMBtu
08 2.2511: Insulate bare equipment $535 $315 - $535
-
MMBtu
09 2.2135: Repair and eliminate steam leaks $13,080 $500 - $13,080
-
MMBtu
10 2.6218: Turn off equipment when not in use $45,615 - - $45,615
-
MMBtu
11 2.6221: Use most efficient equipment at it's maximum capacity and less efficient equipment only when necessary $2,350 - - $2,350
-
MMBtu
TOTAL RECOMMENDED $81,572 $32,762 $6,409
211,020
kWh
$75,163
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs