| Assessment Year | 2017 |
|---|---|
| Principal Product | Printing services |
| NAICS | 323111: Commercial Printing (except Screen and Books) |
| SIC | 2752: Commercial Printing, Lithographic |
| Sales Range | $10 M to 50M |
| # of Employees | 70 |
| Plant Area |
25,000
ft2
|
| Annual Production | 100,000
pieces
|
| Production Hrs. Annual | 3,302
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $99,902 | 1,212,320 |
kWh
|
$0.082 | |
| Electricity Demand | $79,486 | 5,012 |
kW-mo/yr
|
$15.86 | |
| Electricity Fees | $8,788 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $5,727 | 503,404 |
Tgal
|
$0.011 | |
| TOTAL YEARLY COSTS | $193,903 | ||||
| RECOMMENDED SAVINGS* | $39,371 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Ancillary Material Cost Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $26,295 | $200 |
$15,472
187,770
kWh
|
$10,823
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,087 | $5,774 |
$4,169
50,600
kWh
|
$2,918
-
kW-mo/yr
|
- | - | - | |
| 03 | 3.5316: Contract a wood pallet recycling company | $3,510 | $60 | - | - | - | $3,510 | - | |
| 04 | 3.4151: Minimize water usage | $912 | $2,243 | - | - |
$912
-
Tgal
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $787 | $60 |
$422
5,118
kWh
|
$365
-
kW-mo/yr
|
- | - | - | |
| 06 | 4.652: Replace existing equipment with more suitable substitutes | $780 | $325 |
$113
1,369
kWh
|
$73
-
kW-mo/yr
|
- | - | $594 | |
| TOTAL RECOMMENDED | $39,371 | $8,662 |
$20,176
244,857
kWh
|
$14,179
-
kW-mo/yr
|
$912
-
Tgal
|
$3,510 | $594 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Ancillary Material Cost Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs