Assessment Year | 1983 |
---|---|
Principal Product | LPG PUMPS/COMPRESSORS |
NAICS |
n/a
|
SIC | 3561: Pumps and Pumping Equipment |
Sales Range | $10 M to 50M |
# of Employees | 120 |
Plant Area |
n/a
|
Annual Production | 11,000
pieces
|
Production Hrs. Annual | 2,200
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $70,634 | 1,487,104 |
kWh
|
$0.047 |
Natural Gas | $9,194 | 2,910 |
MMBtu
|
$3.16 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,030 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,932 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7314: Reduce ventilation air | $1,596 | $69 |
$233
7,034
kWh
|
$1,363
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,098 | $136 |
$9,098
267,585
kWh
|
- | |
03 | 2.7261: Install timers and/or thermostats | $6,118 | $439 |
$2,508
73,857
kWh
|
$3,610
-
MMBtu
|
|
04 | 2.7314: Reduce ventilation air | $2,218 | $1,863 |
$435
12,896
kWh
|
$1,783
-
MMBtu
|
|
TOTAL RECOMMENDED | $19,030 | $2,507 |
$12,274
361,372
kWh
|
$6,756
-
MMBtu
|
||
TOTAL IMPLEMENTED | $9,932 | $2,371 |
$3,176
93,787
kWh
|
$6,756
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs