| Assessment Year | 1982 |
|---|---|
| Principal Product | BUTTERFLY VALVES |
| NAICS |
n/a
|
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 120 |
| Plant Area |
n/a
|
| Annual Production | 70,000
pieces
|
| Production Hrs. Annual | 3,400
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $60,700 | 1,465,123 |
kWh
|
$0.041 |
| Natural Gas | $45,000 | 15,000 |
MMBtu
|
$3.00 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $6,687 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,687 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $707 | $56 |
$707
21,102
kWh
|
- | |
| 02 | 2.7261: Install timers and/or thermostats | $1,830 | $400 |
$1,830
54,807
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,330 | $1,405 |
$1,330
24,033
kWh
|
- | |
| 04 | 2.7261: Install timers and/or thermostats | $1,749 | $560 | - |
$1,749
-
MMBtu
|
|
| 05 | 2.7261: Install timers and/or thermostats | $485 | - | - |
$485
-
MMBtu
|
|
| 06 | 2.3512: De-energize excess transformer capacity | $586 | - |
$586
17,585
kWh
|
- | |
| TOTAL RECOMMENDED | $6,687 | $2,421 |
$4,453
117,527
kWh
|
$2,234
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $6,687 | $2,421 |
$4,453
117,527
kWh
|
$2,234
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs