| Assessment Year | 1982 |
|---|---|
| Principal Product | LARGE TRUCKS |
| NAICS |
n/a
|
| SIC | 3531: Construction Machinery and Equipment |
| Sales Range | $100 M to 500M |
| # of Employees | 250 |
| Plant Area |
n/a
|
| Annual Production | 1,200
pieces
|
| Production Hrs. Annual | 2,000
hrs
|
| Location (State) | Oklahoma |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $97,700 | 2,796,893 |
kWh
|
$0.035 |
| Natural Gas | $88,720 | 33,720 |
MMBtu
|
$2.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $70,785 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7261: Install timers and/or thermostats | $47,030 | $3,200 | - |
$47,030
-
MMBtu
|
|
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,390 | $500 |
$10,390
273,447
kWh
|
- | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,550 | $23,600 |
$12,550
226,553
kWh
|
- | |
| 04 | 2.7494: Install storm windows and doors | $815 | $3,360 | - |
$815
-
MMBtu
|
|
| TOTAL RECOMMENDED | $70,785 | $30,660 |
$22,940
500,000
kWh
|
$47,845
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs