Assessment Year | 1982 |
---|---|
Principal Product | LARGE TRUCKS |
NAICS |
n/a
|
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $100 M to 500M |
# of Employees | 250 |
Plant Area |
n/a
|
Annual Production | 1,200
pieces
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,700 | 2,796,893 |
kWh
|
$0.035 |
Natural Gas | $88,720 | 33,720 |
MMBtu
|
$2.63 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,785 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.7261: Install timers and/or thermostats | $47,030 | $3,200 | - |
$47,030
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,390 | $500 |
$10,390
273,447
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,550 | $23,600 |
$12,550
226,553
kWh
|
- | |
04 | 2.7494: Install storm windows and doors | $815 | $3,360 | - |
$815
-
MMBtu
|
|
TOTAL RECOMMENDED | $70,785 | $30,660 |
$22,940
500,000
kWh
|
$47,845
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs