ITAC Assessment: OK0044
ITAC logo
ITAC Assessment: OK0044
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product LARGE TRUCKS
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 250
Plant Area
n/a
Annual Production 1,200
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $97,700 2,796,893
kWh
Natural Gas $88,720 33,720
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $70,785 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7261: Install timers and/or thermostats $47,030 $3,200 - $47,030
-
MMBtu
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,390 $500 $10,390
273,447
kWh
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $12,550 $23,600 $12,550
226,553
kWh
-
04 2.7494: Install storm windows and doors $815 $3,360 - $815
-
MMBtu
TOTAL RECOMMENDED $70,785 $30,660 $22,940
500,000
kWh
$47,845
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs