ITAC Assessment: OK0038
ITAC logo
ITAC Assessment: OK0038
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1982
Principal Product HEAVY TRUCK CHASSIS
NAICS
n/a
SIC 3531: Construction Machinery and Equipment
Sales Range $100
M
to 500
M
# of Employees 500
Plant Area
n/a
Annual Production 1,200
pieces
Production Hrs. Annual 2,000
hrs
Location (State) Oklahoma

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $243,095 7,153,869
kWh
Natural Gas $92,990 35,531
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $28,253 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4221: Install compressor air intakes in coolest locations $217 $313 $217
6,448
kWh
-
02 2.7231: Use radiant heater for spot heating $23,027 $29,970 - $23,027
-
MMBtu
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $259 $165 $259
7,620
kWh
-
04 2.7494: Install storm windows and doors $4,750 $17,358 - $4,750
-
MMBtu
TOTAL RECOMMENDED $28,253 $47,806 $476
14,068
kWh
$27,777
-
MMBtu
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs