Assessment Year | 1982 |
---|---|
Principal Product | HEAT EXCHANGERS |
NAICS |
n/a
|
SIC | 3443: Fabricated Plate Work (Boiler Shops) |
Sales Range | $10 M to 50M |
# of Employees | 300 |
Plant Area |
n/a
|
Annual Production | 300
pieces
|
Production Hrs. Annual | 3,680
hrs
|
Location (State) | Oklahoma |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $154,176 | 4,410,024 |
kWh
|
$0.035 |
Natural Gas | $107,778 | 42,946 |
MMBtu
|
$2.51 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $55,699 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,616 | $135 |
$7,616
254,396
kWh
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $501 | $121 |
$501
16,706
kWh
|
- | |
03 | 2.7492: Use proper thickness of insulation on building envelope | $44,316 | $156,240 | - |
$44,316
-
MMBtu
|
|
04 | 2.7111: Reduce illumination to minimum necessary levels | $275 | $80 |
$275
8,206
kWh
|
- | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $656 | $560 |
$656
17,585
kWh
|
- | |
06 | 2.3212: Optimize plant power factor | $2,335 | $6,560 |
$2,335
-
kWh
|
- | |
TOTAL RECOMMENDED | $55,699 | $163,696 |
$11,383
296,893
kWh
|
$44,316
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs