| Assessment Year | 2000 |
|---|---|
| Principal Product | Print Rolls |
| NAICS |
n/a
|
| SIC | 2822: Synthetic Rubber (Vulcanizable Elastomers) |
| Sales Range | $10 M to 50M |
| # of Employees | 30 |
| Plant Area |
18,000
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 2,850
hrs
|
| Location (State) | Virginia |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $37,375 | 810,961 |
kWh
|
$0.046 |
| Electricity Demand | $14,340 | - |
|
- |
| Electricity Fees | $1,226 | - |
|
- |
| Natural Gas | $25,277 | 3,601 |
MMBtu
|
$7.02 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $10,398 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,241 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6231: Utilize controls to operate equipment only when needed | $596 | $888 |
$596
14,361
kWh
|
- | - | |
| 02 | 2.7224: Reduce space conditioning during non-working hours | $1,526 | $180 |
$1,526
57,444
kWh
|
- | - | |
| 03 | 2.2113: Repair or replace steam traps | $4,241 | $1,420 | - | - |
$4,241
-
MMBtu
|
|
| 04 | 2.4314: Use synthetic lubricant | $208 | $16 |
$138
3,810
kWh
|
$70
-
kW-mo/yr
|
- | |
| 05 | 2.7135: Install occupancy sensors | $1,083 | - |
$1,083
23,740
kWh
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,644 | $4,032 |
$1,762
38,101
kWh
|
$882
-
kW-mo/yr
|
- | |
| 07 | 2.7135: Install occupancy sensors | $100 | $95 |
$100
2,052
kWh
|
- | - | |
| TOTAL RECOMMENDED | $10,398 | $6,631 |
$5,205
139,508
kWh
|
$952
-
kW-mo/yr
|
$4,241
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,241 | $1,420 | - | - |
$4,241
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs