ITAC Assessment: OD0157
ITAC logo
ITAC Assessment: OD0157
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Print Rolls
NAICS
n/a
SIC 2822: Synthetic Rubber (Vulcanizable Elastomers)
Sales Range $10
M
to 50
M
# of Employees 30
Plant Area 18,000
ft2
Annual Production 0
units
Production Hrs. Annual 2,850
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,375 810,961
kWh
Electricity Demand $14,340 -
Electricity Fees $1,226 -
Natural Gas $25,277 3,601
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $10,398 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,241

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.6231: Utilize controls to operate equipment only when needed $596 $888 $596
14,361
kWh
- -
02 2.7224: Reduce space conditioning during non-working hours $1,526 $180 $1,526
57,444
kWh
- -
03 2.2113: Repair or replace steam traps $4,241 $1,420 - - $4,241
-
MMBtu
04 2.4314: Use synthetic lubricant $208 $16 $138
3,810
kWh
$70
-
kW-mo/yr
-
05 2.7135: Install occupancy sensors $1,083 - $1,083
23,740
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,644 $4,032 $1,762
38,101
kWh
$882
-
kW-mo/yr
-
07 2.7135: Install occupancy sensors $100 $95 $100
2,052
kWh
- -
TOTAL RECOMMENDED $10,398 $6,631 $5,205
139,508
kWh
$952
-
kW-mo/yr
$4,241
-
MMBtu
TOTAL IMPLEMENTED $4,241 $1,420 - - $4,241
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs