Assessment Year | 1999 |
---|---|
Principal Product | Structural Lumber |
NAICS |
n/a
|
SIC | 2421: Sawmills and Planing Mills, General |
Sales Range | $10 M to 50M |
# of Employees | 54 |
Plant Area |
50,000
ft2
|
Annual Production | 35,000,000
units
|
Production Hrs. Annual | 2,375
hrs
|
Location (State) | Virginia |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $168,066 | 4,168,816 |
kWh
|
$0.040 |
Electricity Demand | $149,218 | 17,539 |
kW-mo/yr
|
$8.51 |
Electricity Fees | $4,283 | - |
|
- |
Natural Gas | $4,531 | 644 |
MMBtu
|
$7.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,585 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,386 | $1,800 |
$3,386
84,115
kWh
|
- | - | - | |
02 | 2.4113: Install motor voltage controller on lightly loaded motors | $854 | $1,290 |
$377
9,379
kWh
|
$477
-
kW-mo/yr
|
- | - | |
03 | 2.7224: Reduce space conditioning during non-working hours | $565 | $420 |
$565
18,757
kWh
|
- | - | - | |
04 | 4.231: Purchase equipment instead of leasing | $26,400 | $47,500 | - | - | $26,400 | - | |
05 | 4.514: Re-arrange equipment layout to reduce handling costs | $1,380 | $1,155 | - | - | - | $1,380 | |
TOTAL RECOMMENDED | $32,585 | $52,165 |
$4,328
112,251
kWh
|
$477
-
kW-mo/yr
|
$26,400 | $1,380 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs