ITAC Assessment: OD0083
ITAC logo
ITAC Assessment: OD0083
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Plastic Cups
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 57
Plant Area 77,000
ft2
Annual Production 17,000,000
pieces
Production Hrs. Annual 8,736
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $231,093 13,048,652
kWh
Electricity Demand $296,533 24,758
kW-mo/yr
Electricity Fees $58,371 -
LPG $14,718 1,145
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $517,462 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,624 $1,487 n/a $1,360
76,788
kWh
$1,264
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $1,747 $5,202 n/a $898
50,703
kWh
$849
-
kW-mo/yr
-
03 2.7447: Install vinyl strip / high speed / air curtain doors $1,031 $2,091 n/a $1,031
58,324
kWh
- -
04 2.2437: Recover waste heat from equipment $12,028 $5,691 n/a $5,846
330,305
kWh
$6,182
-
kW-mo/yr
-
05 4.611: Begin a practice of predictive / preventative maintenance $500,032 $30,482 n/a - - $500,032
TOTAL RECOMMENDED $517,462 $44,953 $9,135
516,120
kWh
$8,295
-
kW-mo/yr
$500,032
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs