ITAC Assessment: OD0061
ITAC logo
ITAC Assessment: OD0061
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Commercial printing; magazines, catalogs, inserts
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 82
Plant Area 51,670
ft2
Annual Production 75,000,000
pieces
Production Hrs. Annual 5,550
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,963 2,626,612
kWh
Electricity Demand $94,587 13,792
kW-mo/yr
Electricity Fees $15,969 -
Natural Gas $20,461 4,318
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,354 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $189 $160 $189
10,551
kWh
- - - -
02 2.7261: Install timers and/or thermostats $337 $270 $337
18,757
kWh
- - - -
03 2.2442: Preheat combustion air with waste heat $11,625 $5,634 - - $11,625
-
MMBtu
- -
04 2.4133: Use most efficient type of electric motors $161 $485 $88
4,982
kWh
$73
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,584 $6,110 $818
45,721
kWh
$766
-
kW-mo/yr
- - -
06 2.7135: Install occupancy sensors $408 $689 $408
22,860
kWh
- - - -
07 3.5212: Regrind, reuse, or sell scrap plastic parts $46 - - - - - $46
-
lb
08 3.8211: Convert to aqueous cleaning system $3,004 $5,050 - - - $3,004
-
gal
-
TOTAL RECOMMENDED $17,354 $18,398 $1,840
102,871
kWh
$839
-
kW-mo/yr
$11,625
-
MMBtu
$3,004
-
gal
$46
-
lb
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs