ITAC Assessment: OD0056
ITAC logo
ITAC Assessment: OD0056
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Escalators, autowalks
NAICS
n/a
SIC 3534: Elevators and Moving Stairways
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 68,000
ft2
Annual Production 250
pieces
Production Hrs. Annual 2,996
hrs
Location (State) Virginia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,199 926,436
kWh
Electricity Demand $17,125 3,040
kW-mo/yr
Electricity Fees $1,487 -
Natural Gas $11,312 2,213
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,988 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
01 2.2437: Recover waste heat from equipment $4,344 $701 n/a - - $4,344
-
MMBtu
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $154 $1,365 n/a $101
2,052
kWh
$53
-
kW-mo/yr
- -
03 2.4133: Use most efficient type of electric motors $269 $520 n/a $233
4,689
kWh
$36
-
kW-mo/yr
- -
04 2.7261: Install timers and/or thermostats $1,815 $1,365 n/a $1,815
35,463
kWh
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $580 $320 n/a $580
11,430
kWh
- - -
06 3.6192: Use a less expensive method of waste removal $7,826 $8,120 n/a - - - $7,826
-
lb
TOTAL RECOMMENDED $14,988 $12,391 $2,729
53,634
kWh
$89
-
kW-mo/yr
$4,344
-
MMBtu
$7,826
-
lb
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs