ITAC Assessment: NV0156
ITAC logo
ITAC Assessment: NV0156
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product ball and roller bearings
NAICS
n/a
SIC 3562: Ball and Roller Bearings
Sales Range $10
M
to 50
M
# of Employees 26
Plant Area
n/a
Annual Production 100,000
pieces
Production Hrs. Annual 2,125
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $26,685 639,457
kWh
Electricity Demand $17,980 1,937
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $11,405 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,207

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1311: Replace electrically-operated equipment with fossil fuel equipment $10,198 $375 $6,580
157,680
kWh
$4,009
-
kW-mo/yr
$(-391.0)
-
MMBtu
02 2.4226: Use / purchase optimum sized compressor $1,047 $4,500 $74
21,594
kWh
$973
-
kW-mo/yr
-
03 2.4133: Use most efficient type of electric motors $160 $297 $66
1,583
kWh
$94
-
kW-mo/yr
-
TOTAL RECOMMENDED $11,405 $5,172 $6,720
180,857
kWh
$5,076
-
kW-mo/yr
$(-391.0)
-
MMBtu
TOTAL IMPLEMENTED $1,207 $4,797 $140
23,177
kWh
$1,067
-
kW-mo/yr
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs