ITAC Assessment: NV0125
ITAC logo
ITAC Assessment: NV0125
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Newspapers
NAICS
n/a
SIC 2711: Newspapers: Publishing, or Publishing and Printing
Sales Range $5
M
to 10
M
# of Employees 100
Plant Area 18,000
ft2
Annual Production 5,304,000
pieces
Production Hrs. Annual 3,744
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $35,162 427,608
kWh
Electricity Demand $6,635 1,529
kW-mo/yr
Electricity Fees $986 -
Natural Gas $4,979 749
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $119,408 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $93,329

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.4111: Utilize energy-efficient belts and other improved mechanisms $640 $640 $475
5,862
kWh
$165
-
kW-mo/yr
- - - -
02 2.4224: Upgrade controls on compressors $354 $110 $353
4,396
kWh
- $1 - - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $158 - $105
1,172
kWh
$53
-
kW-mo/yr
- - - -
04 2.7135: Install occupancy sensors $701 $825 $470
5,862
kWh
$230
-
kW-mo/yr
$1 - - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $5,223 $6,789 $4,500
54,807
kWh
$712
-
kW-mo/yr
$11 - - -
06 2.7233: Use properly designed and sized hvac equipment $24,200 $102,400 - - - - $24,200 -
07 3.6192: Use a less expensive method of waste removal $860 - - - - - $860 -
08 3.8214: Use water-based developers and finishers $160 - - - - - $160 -
09 4.111: Add equipment/ operators to reduce production bottleneck $74,476 $250,000 - - - - $20,476 $54,000
10 4.441: Install automatic packing equipment $12,636 $55,000 - - - $12,636 - -
TOTAL RECOMMENDED $119,408 $415,764 $5,903
72,099
kWh
$1,160
-
kW-mo/yr
$13 $12,636 $45,696 $54,000
TOTAL IMPLEMENTED $93,329 $312,539 $5,328
65,065
kWh
$877
-
kW-mo/yr
$12 $12,636 $20,476 $54,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs