Assessment Year | 1998 |
---|---|
Principal Product | Newspapers |
NAICS |
n/a
|
SIC | 2711: Newspapers: Publishing, or Publishing and Printing |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
18,000
ft2
|
Annual Production | 5,304,000
pieces
|
Production Hrs. Annual | 3,744
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,162 | 427,608 |
kWh
|
$0.082 |
Electricity Demand | $6,635 | 1,529 |
kW-mo/yr
|
$4.34 |
Electricity Fees | $986 | - |
|
- |
Natural Gas | $4,979 | 749 |
MMBtu
|
$6.65 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $119,408 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $93,329 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $640 | $640 |
$475
5,862
kWh
|
$165
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4224: Upgrade controls on compressors | $354 | $110 |
$353
4,396
kWh
|
- | $1 | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $158 | - |
$105
1,172
kWh
|
$53
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.7135: Install occupancy sensors | $701 | $825 |
$470
5,862
kWh
|
$230
-
kW-mo/yr
|
$1 | - | - | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,223 | $6,789 |
$4,500
54,807
kWh
|
$712
-
kW-mo/yr
|
$11 | - | - | - | |
06 | 2.7233: Use properly designed and sized hvac equipment | $24,200 | $102,400 | - | - | - | - | $24,200 | - | |
07 | 3.6192: Use a less expensive method of waste removal | $860 | - | - | - | - | - | $860 | - | |
08 | 3.8214: Use water-based developers and finishers | $160 | - | - | - | - | - | $160 | - | |
09 | 4.111: Add equipment/ operators to reduce production bottleneck | $74,476 | $250,000 | - | - | - | - | $20,476 | $54,000 | |
10 | 4.441: Install automatic packing equipment | $12,636 | $55,000 | - | - | - | $12,636 | - | - | |
TOTAL RECOMMENDED | $119,408 | $415,764 |
$5,903
72,099
kWh
|
$1,160
-
kW-mo/yr
|
$13 | $12,636 | $45,696 | $54,000 | ||
TOTAL IMPLEMENTED | $93,329 | $312,539 |
$5,328
65,065
kWh
|
$877
-
kW-mo/yr
|
$12 | $12,636 | $20,476 | $54,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs