Assessment Year | 2004 |
---|---|
Principal Product | Electrically Welded Structural Steel tube |
NAICS | 331221: Rolled Steel Shape Manufacturing |
SIC | 3312: Steel Works, Blast Furnaces (Including Coke Ovens), and Rolling Mills |
Sales Range | $10 M to 50M |
# of Employees | 82 |
Plant Area |
302,252
ft2
|
Annual Production | 95,000
ton
|
Production Hrs. Annual | 3,824
hrs
|
Location (State) | Indiana |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $141,335 | 4,408,435 |
kWh
|
$0.032 |
Electricity Demand | $214,549 | 29,238 |
kW-mo/yr
|
$7.34 |
Electricity Fees | $5,876 | - |
|
- |
Natural Gas | $102,093 | 10,983 |
MMBtu
|
$9.30 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,365 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,876 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,066 | $2,100 |
$1,202
37,568
kWh
|
$864
-
kW-mo/yr
|
- | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,003 | $199 |
$1,003
31,345
kWh
|
- | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $24,747 | $74,730 |
$14,036
438,599
kWh
|
$9,875
-
kW-mo/yr
|
$(-1,327.0) | $2,163 | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $999 | $4,888 |
$445
13,892
kWh
|
$456
-
kW-mo/yr
|
$1 | $97 | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,807 | $2,963 |
$235
7,358
kWh
|
$74
-
kW-mo/yr
|
$650 | $848 | |
06 | 2.7135: Install occupancy sensors | $743 | $4,033 |
$620
19,317
kWh
|
$123
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $31,365 | $88,913 |
$17,541
548,079
kWh
|
$11,392
-
kW-mo/yr
|
$(-676.0) | $3,108 | ||
TOTAL IMPLEMENTED | $4,876 | $5,262 |
$2,440
76,271
kWh
|
$938
-
kW-mo/yr
|
$650 | $848 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs