Assessment Year | 1998 |
---|---|
Principal Product | Unsupported Plastic Film and Sheet |
NAICS |
n/a
|
SIC | 3081: Unsupported Plastics Film and Sheet |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
27,000
ft2
|
Annual Production | 12,000,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $97,957 | 2,365,475 |
kWh
|
$0.041 |
Electricity Demand | $39,037 | 4,010 |
kW-mo/yr
|
$9.73 |
Electricity Fees | $5,593 | - |
|
- |
Natural Gas | $1,232 | 222 |
MMBtu
|
$5.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $12,539 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $7,698 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $2,663 | $3,333 | - | - | $2,663 | - | - | |
02 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $331 | $180 |
$275
6,741
kWh
|
$50
-
kW-mo/yr
|
$6 | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,687 | $56 |
$1,397
33,705
kWh
|
$257
-
kW-mo/yr
|
$33 | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,324 | - |
$1,097
26,377
kWh
|
$201
-
kW-mo/yr
|
$26 | - | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $2,870 | - | - | - | $2,870 | - | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $1,834 | $3,260 | - | - | - | - | $1,834 | |
07 | 3.6192: Use a less expensive method of waste removal | $1,830 | - | - | - | - | $1,830 | - | |
TOTAL RECOMMENDED | $12,539 | $6,829 |
$2,769
66,823
kWh
|
$508
-
kW-mo/yr
|
$5,598 | $1,830 | $1,834 | ||
TOTAL IMPLEMENTED | $7,698 | $6,773 |
$275
6,741
kWh
|
$50
-
kW-mo/yr
|
$5,539 | - | $1,834 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs