ITAC Assessment: NV0114
ITAC logo
ITAC Assessment: NV0114
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Electronic Computers
NAICS
n/a
SIC 3571: Electronic Computers
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 89,739
ft2
Annual Production 4,500
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $36,836 882,767
kWh
Electricity Demand $31,747 3,421
kW-mo/yr
Electricity Fees $2,596 -
Natural Gas $12,620 1,949
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,516 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings
01 2.4221: Install compressor air intakes in coolest locations $332 $275 $152
3,517
kWh
$173
-
kW-mo/yr
$7
02 2.7142: Utilize higher efficiency lamps and/or ballasts $10,835 $13,808 $6,765
162,075
kWh
$3,858
-
kW-mo/yr
$212
03 2.7145: Install skylights $1,349 $3,308 $558
13,482
kWh
$765
-
kW-mo/yr
$26
TOTAL RECOMMENDED $12,516 $17,391 $7,475
179,074
kWh
$4,796
-
kW-mo/yr
$245
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs