| Assessment Year | 2009 |
|---|---|
| Principal Product | aluminum die castings |
| NAICS | 331314: Secondary Smelting and Alloying of Aluminum |
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $50 M to 100M |
| # of Employees | 190 |
| Plant Area |
225,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 4,000
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,423,109 | 16,983,600 |
kWh
|
$0.084 |
| Natural Gas | $1,359,790 | 157,608 |
MMBtu
|
$8.63 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $143,861 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.2442: Preheat combustion air with waste heat | $87,552 | $18,000 | - |
$87,552
-
MMBtu
|
|
| 02 | 2.2515: Use optimum thickness insulation | $1,717 | $4,200 | - |
$1,717
-
MMBtu
|
|
| 03 | 2.6127: Maintain air filters by cleaning or replacement | $11,665 | $2,900 |
$11,665
125,393
kWh
|
- | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $739 | $850 |
$739
7,924
kWh
|
- | |
| 05 | 2.4131: Size electric motors for peak operating efficiency | $710 | $1,993 |
$710
7,892
kWh
|
- | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $40,988 | $59,705 |
$40,988
446,196
kWh
|
- | |
| 07 | 2.7135: Install occupancy sensors | $490 | $640 |
$490
5,856
kWh
|
- | |
| TOTAL RECOMMENDED | $143,861 | $88,288 |
$54,592
593,261
kWh
|
$89,269
-
MMBtu
|
||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs