Assessment Year | 1998 |
---|---|
Principal Product | Remanufactured Industrial Parts |
NAICS |
n/a
|
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 40 |
Plant Area |
25,000
ft2
|
Annual Production | 38,000,000
units
|
Production Hrs. Annual | 6,214
hrs
|
Location (State) | California |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $49,214 | 836,166 |
kWh
|
$0.059 |
Electricity Demand | $15,056 | 2,327 |
kW-mo/yr
|
$6.47 |
Electricity Fees | $5,219 | - |
|
- |
Natural Gas | $1,133 | 137 |
MMBtu
|
$8.27 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,707 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,517 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $1,042 | $768 |
$776
13,189
kWh
|
$192
-
kW-mo/yr
|
$74 | - | |
02 | 2.3522: Increase electrical conductor size to reduce distribution losses | $11,472 | $15,808 |
$7,079
120,164
kWh
|
$3,570
-
kW-mo/yr
|
$823 | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $259 | - |
$192
3,224
kWh
|
$48
-
kW-mo/yr
|
$19 | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,992 | $350 |
$2,158
36,635
kWh
|
$1,549
-
kW-mo/yr
|
$285 | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $148 | $252 |
$110
1,758
kWh
|
$28
-
kW-mo/yr
|
$10 | - | |
06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $794 | $220 | - | - | - |
$794
-
lb
|
|
TOTAL RECOMMENDED | $17,707 | $17,398 |
$10,315
174,970
kWh
|
$5,387
-
kW-mo/yr
|
$1,211 |
$794
-
lb
|
||
TOTAL IMPLEMENTED | $16,517 | $16,378 |
$9,429
160,023
kWh
|
$5,167
-
kW-mo/yr
|
$1,127 |
$794
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs