ITAC Assessment: NV0106
ITAC logo
ITAC Assessment: NV0106
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Slurry Valves and Feeders
NAICS
n/a
SIC 3494: Valves and Pipe Fittings, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 47,000
ft2
Annual Production 7,330
pieces
Production Hrs. Annual 6,266
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $59,354 1,422,333
kWh
Electricity Demand $35,032 3,775
kW-mo/yr
Electricity Fees $2,500 -
Natural Gas $26,330 5,073
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $23,313 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $11,109

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Water Consumption Savings
01 2.1213: Direct warmest air to combustion intake $388 $210 - - - $388
-
MMBtu
- - - -
02 2.2515: Use optimum thickness insulation $304 $370 - - - $304
-
MMBtu
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $4,070 $13,450 $2,798
67,116
kWh
$1,192
-
kW-mo/yr
$80 - - - - -
04 2.7261: Install timers and/or thermostats $162 - $114
2,638
kWh
$45
-
kW-mo/yr
$3 - - - - -
05 3.1161: Eliminate/reduce an operation $9,796 - - - - - $9,796
-
gal
- - -
06 3.1191: Change procedures / equipment / operating conditions $1,753 $4,700 - - - - - $1,753
-
lb
- -
07 3.4116: Meter recycled water (to reduce sewer charges) $521 $243 - - - - - - - $521
-
Tgal
08 3.5314: Use in-process recycling whenever possible $327 $50 - - - - - $327
-
lb
- -
09 3.5315: Lease / purchase baler; sell cardboard to recycler $986 - - - - - - $986
-
lb
- -
10 3.5316: Contract a wood pallet recycling company $711 - - - - - - $711
-
lb
- -
11 3.7131: Use a rag recycle service $4,295 - - - - - - - $4,295
-
lb
-
TOTAL RECOMMENDED $23,313 $19,023 $2,912
69,754
kWh
$1,237
-
kW-mo/yr
$83 $692
-
MMBtu
$9,796
-
gal
$3,777
-
lb
$4,295
-
lb
$521
-
Tgal
TOTAL IMPLEMENTED $11,109 $50 - - - - $9,796
-
gal
$1,313
-
lb
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings Solid Waste (haz) Savings Water Consumption Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs