Assessment Year | 1998 |
---|---|
Principal Product | Lightning Protection Equipment |
NAICS |
n/a
|
SIC | 3643: Current-Carrying Wiring Devices |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
53,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 4,080
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $14,017 | 335,873 |
kWh
|
$0.042 |
Electricity Demand | $11,470 | 1,236 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $600 | - |
|
- |
Natural Gas | $4,706 | 715 |
MMBtu
|
$6.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $69,600 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $69,567 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $179 | $137 |
$108
2,638
kWh
|
$71
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7134: Use photocell controls | $550 | $200 |
$238
5,569
kWh
|
$312
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7243: Improve air circulation with destratification fans / other methods | $912 | $750 | - | - |
$912
-
MMBtu
|
- | - | - | |
04 | 4.652: Replace existing equipment with more suitable substitutes | $44,986 | $9,960 | - | - | - | - | - | $44,986 | |
05 | 4.114: Add/modify equipment to improve drying process | $22,940 | $7,800 | - | - | - | - | $22,940 | - | |
06 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $33 | - | - | - | - |
$33
-
lb
|
- | - | |
TOTAL RECOMMENDED | $69,600 | $18,847 |
$346
8,207
kWh
|
$383
-
kW-mo/yr
|
$912
-
MMBtu
|
$33
-
lb
|
$22,940 | $44,986 | ||
TOTAL IMPLEMENTED | $69,567 | $18,847 |
$346
8,207
kWh
|
$383
-
kW-mo/yr
|
$912
-
MMBtu
|
- | $22,940 | $44,986 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs