Assessment Year | 1998 |
---|---|
Principal Product | Plastic Products, Not Elsewhere Classified |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 130 |
Plant Area |
450,000
ft2
|
Annual Production | 445,000
lb
|
Production Hrs. Annual | 4,394
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $46,103 | 1,094,373 |
kWh
|
$0.042 |
Electricity Demand | $36,229 | 3,904 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $2,298 | - |
|
- |
Natural Gas | $3,990 | 739 |
MMBtu
|
$5.40 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,138 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,260 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $917 | $150 |
$899
21,688
kWh
|
- | $18 | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $233 | $326 |
$141
3,517
kWh
|
$86
-
kW-mo/yr
|
$6 | - | - | |
03 | 2.2437: Recover waste heat from equipment | $1,558 | $1,890 | - | - | - |
$1,558
-
MMBtu
|
- | |
04 | 2.4221: Install compressor air intakes in coolest locations | $443 | $135 |
$434
10,551
kWh
|
- | $9 | - | - | |
05 | 2.7134: Use photocell controls | $2,667 | $495 |
$2,054
137,163
kWh
|
$561
-
kW-mo/yr
|
$52 | - | - | |
06 | 4.422: Utilize outside contracting | $42,320 | $25,000 | - | - | - | - | $42,320 | |
TOTAL RECOMMENDED | $48,138 | $27,996 |
$3,528
172,919
kWh
|
$647
-
kW-mo/yr
|
$85 |
$1,558
-
MMBtu
|
$42,320 | ||
TOTAL IMPLEMENTED | $4,260 | $1,106 |
$3,528
172,919
kWh
|
$647
-
kW-mo/yr
|
$85 | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs