ITAC Assessment: NV0095
ITAC logo
ITAC Assessment: NV0095
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Wood Cabinets
NAICS
n/a
SIC 2434: Wood Kitchen Cabinets
Sales Range $5
M
to 10
M
# of Employees 85
Plant Area 40,000
ft2
Annual Production 3,500
pieces
Production Hrs. Annual 4,397
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $30,538 504,103
kWh
Electricity Demand $10,358 1,358
kW-mo/yr
Electricity Fees $3,400 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $22,548 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,713

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings
01 2.7111: Reduce illumination to minimum necessary levels $4,185 $276 $3,138
51,876
kWh
$1,047
-
kW-mo/yr
- -
02 2.4221: Install compressor air intakes in coolest locations $117 $75 $117
2,052
kWh
- - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $1,650 $244 $1,159
19,050
kWh
$491
-
kW-mo/yr
- -
04 2.4133: Use most efficient type of electric motors $494 $398 $368
6,155
kWh
$126
-
kW-mo/yr
- -
05 2.6212: Turn off equipment during breaks, reduce operating time $2,127 $200 $1,972
32,532
kWh
- $155 -
06 2.6218: Turn off equipment when not in use $1,154 $200 $1,070
17,585
kWh
- $84 -
07 4.111: Add equipment/ operators to reduce production bottleneck $12,821 $5,600 - - - $12,821
TOTAL RECOMMENDED $22,548 $6,993 $7,824
129,250
kWh
$1,664
-
kW-mo/yr
$239 $12,821
TOTAL IMPLEMENTED $16,713 $6,473 $3,527
58,324
kWh
$126
-
kW-mo/yr
$239 $12,821
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs