Assessment Year | 2004 |
---|---|
Principal Product | Asphalt paving mixtures |
NAICS | 324121: Asphalt Paving Mixture and Block Manufacturing |
SIC | 2951: Asphalt Paving Mixtures and Blocks |
Sales Range | $10 M to 50M |
# of Employees | 210 |
Plant Area |
60,000
ft2
|
Annual Production | 500,000
ton
|
Production Hrs. Annual | 3,627
hrs
|
Location (State) | Colorado |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $55,196 | 2,289,155 |
kWh
|
$0.024 |
Electricity Demand | $195,071 | 13,985 |
kW-mo/yr
|
$13.95 |
Electricity Fees | $1,500 | - |
|
- |
Natural Gas | $370,578 | 81,172 |
MMBtu
|
$4.57 |
Fuel Oil #2 | $27,985 | 3,265 |
MMBtu
|
$8.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $17,559 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,959 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $6,340 | $8,790 |
$1,960
74,500
kWh
|
$4,380
-
kW-mo/yr
|
- | - | |
02 | 2.2511: Insulate bare equipment | $5,600 | $18,700 | - | - | - |
$5,600
-
MMBtu
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,710 | $200 |
$1,020
38,400
kWh
|
$1,690
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $579 | $1,136 |
$180
6,809
kWh
|
$399
-
kW-mo/yr
|
- | - | |
05 | 2.2511: Insulate bare equipment | $1,310 | $200 | - | - |
$1,310
-
MMBtu
|
- | |
06 | 2.1133: Adjust burners for efficient operation | $1,020 | $500 | - | - | - |
$1,020
-
MMBtu
|
|
TOTAL RECOMMENDED | $17,559 | $29,526 |
$3,160
119,709
kWh
|
$6,469
-
kW-mo/yr
|
$1,310
-
MMBtu
|
$6,620
-
MMBtu
|
||
TOTAL IMPLEMENTED | $11,959 | $10,826 |
$3,160
119,709
kWh
|
$6,469
-
kW-mo/yr
|
$1,310
-
MMBtu
|
$1,020
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Fuel Oil #2 Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs