ITAC Assessment: NV0093
ITAC logo
ITAC Assessment: NV0093
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Precision Flow Regulating Equipment
NAICS
n/a
SIC 3549: Metalworking Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 128
Plant Area 43,000
ft2
Annual Production 80,000
pieces
Production Hrs. Annual 4,940
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $37,483 859,027
kWh
Electricity Demand $24,082 2,595
kW-mo/yr
Electricity Fees $1,231 -
Natural Gas $5,150 976
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $80,486 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $68,175

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $458 $300 $458
10,551
kWh
- - - -
02 2.3191: Use demand controller or load shedder $426 $147 $100
2,345
kWh
$326
-
kW-mo/yr
- - -
03 2.2437: Recover waste heat from equipment $1,377 $850 - - $1,377
-
MMBtu
- -
04 2.4221: Install compressor air intakes in coolest locations $159 $150 $159
3,517
kWh
- - - -
05 2.4231: Reduce the pressure of compressed air to the minimum required $396 $50 $396
9,086
kWh
- - - -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $4,549 $885 $2,949
67,116
kWh
$1,600
-
kW-mo/yr
- - -
07 2.7111: Reduce illumination to minimum necessary levels $5,633 $513 $3,725
84,701
kWh
$1,908
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $326 $164 $248
5,569
kWh
$78
-
kW-mo/yr
- - -
09 2.4133: Use most efficient type of electric motors $412 $258 $265
6,155
kWh
$147
-
kW-mo/yr
- - -
10 3.7197: Use ultrasonic cleaning $65,000 $16,200 - - - $65,000
-
gal
-
11 3.5315: Lease / purchase baler; sell cardboard to recycler $1,750 $500 - - - - $1,750
-
lb
TOTAL RECOMMENDED $80,486 $20,017 $8,300
189,040
kWh
$4,059
-
kW-mo/yr
$1,377
-
MMBtu
$65,000
-
gal
$1,750
-
lb
TOTAL IMPLEMENTED $68,175 $17,458 $1,278
29,309
kWh
$147
-
kW-mo/yr
- $65,000
-
gal
$1,750
-
lb
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs