ITAC Assessment: NV0088
ITAC logo
ITAC Assessment: NV0088
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Livestock Feed
NAICS
n/a
SIC 2048: Prepared Feed and Feed Ingredients for Animals and Fowls, Except Dogs and Cats
Sales Range $1
M
to 5
M
# of Employees 14
Plant Area 50,000
ft2
Annual Production 9,000
ton
Production Hrs. Annual 2,314
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $47,160 792,204
kWh
Electricity Demand $33,128 5,089
kW-mo/yr
Electricity Fees $3,214 -
Natural Gas $7,440 1,482
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $46,732 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $46,732

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $240 $200 $240
4,103
kWh
- - - - - -
02 2.7261: Install timers and/or thermostats $6,653 $3,100 $6,550
110,199
kWh
$103
-
kW-mo/yr
- - - - -
03 2.7124: Make a practice of turning off lights when not needed $109 $39 $60
879
kWh
$49
-
kW-mo/yr
- - - - -
04 2.4133: Use most efficient type of electric motors $669 $1,148 $426
7,327
kWh
$243
-
kW-mo/yr
- - - - -
05 2.6218: Turn off equipment when not in use $2,073 $900 $1,081
18,171
kWh
$992
-
kW-mo/yr
- - - - -
06 2.2511: Insulate bare equipment $163 $86 - - $163
-
MMBtu
- - - -
07 4.112: Replace old machine with new automatic multi-station tool $5,400 $1,410 - - - - - - $5,400
08 3.5248: Separate and recycle scrap metal to foundry or for sale $4,800 $500 - - - $4,800
-
lb
- - -
09 4.111: Add equipment/ operators to reduce production bottleneck $23,140 $17,160 - - - - - $23,140 -
10 4.521: Clear and rent existing space $3,485 $4,950 - - - - $3,485 - -
TOTAL RECOMMENDED $46,732 $29,493 $8,357
140,679
kWh
$1,387
-
kW-mo/yr
$163
-
MMBtu
$4,800
-
lb
$3,485 $23,140 $5,400
TOTAL IMPLEMENTED $46,732 $29,493 $8,357
140,679
kWh
$1,387
-
kW-mo/yr
$163
-
MMBtu
$4,800
-
lb
$3,485 $23,140 $5,400
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs