ITAC Assessment: NV0085
ITAC logo
ITAC Assessment: NV0085
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Precision Fluid Measuring Devices
NAICS
n/a
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 385
Plant Area 221,000
ft2
Annual Production 360,000
pieces
Production Hrs. Annual 4,862
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $130,996 2,920,574
kWh
Electricity Demand $76,792 8,275
kW-mo/yr
Electricity Fees $(-2,280.0) -
Natural Gas $48,841 9,334
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $47,389 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,491

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $464 $200 $464
10,258
kWh
- - - -
02 2.4133: Use most efficient type of electric motors $219 $196 $145
3,224
kWh
$74
-
kW-mo/yr
- - -
03 2.7111: Reduce illumination to minimum necessary levels $26,223 $6,283 $17,378
386,284
kWh
$8,845
-
kW-mo/yr
- - -
04 2.4221: Install compressor air intakes in coolest locations $701 $400 $701
15,533
kWh
- - - -
05 2.2437: Recover waste heat from equipment $1,705 $2,850 - - $1,705
-
MMBtu
- -
06 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas $2,994 $2,830 - - $2,994
-
MMBtu
- -
07 2.7124: Make a practice of turning off lights when not needed $6,431 $1,520 - - $6,431
-
MMBtu
- -
08 2.2511: Insulate bare equipment $127 $159 $127
2,931
kWh
- - - -
09 2.2514: Cover open tanks $937 $188 - $492
-
kW-mo/yr
$445
-
MMBtu
- -
10 3.5311: Recover and reuse waste material $6,250 $500 - - - $6,250
-
lb
-
11 3.5248: Separate and recycle scrap metal to foundry or for sale $1,000 $150 - - - $1,000
-
lb
-
12 2.3132: Recharge batteries on during off-peak demand periods $338 $147 - - - - $338
TOTAL RECOMMENDED $47,389 $15,423 $18,815
418,230
kWh
$9,411
-
kW-mo/yr
$11,575
-
MMBtu
$7,250
-
lb
$338
TOTAL IMPLEMENTED $5,491 $4,290 $1,437
31,946
kWh
$566
-
kW-mo/yr
$2,150
-
MMBtu
$1,000
-
lb
$338
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs