Assessment Year | 1997 |
---|---|
Principal Product | Precision Fluid Measuring Devices |
NAICS |
n/a
|
SIC | 3841: Surgical and Medical Instruments and Apparatus |
Sales Range | $10 M to 50M |
# of Employees | 385 |
Plant Area |
221,000
ft2
|
Annual Production | 360,000
pieces
|
Production Hrs. Annual | 4,862
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $130,996 | 2,920,574 |
kWh
|
$0.045 |
Electricity Demand | $76,792 | 8,275 |
kW-mo/yr
|
$9.28 |
Electricity Fees | $(-2,280.0) | - |
|
- |
Natural Gas | $48,841 | 9,334 |
MMBtu
|
$5.23 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $47,389 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,491 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $464 | $200 |
$464
10,258
kWh
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $219 | $196 |
$145
3,224
kWh
|
$74
-
kW-mo/yr
|
- | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $26,223 | $6,283 |
$17,378
386,284
kWh
|
$8,845
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $701 | $400 |
$701
15,533
kWh
|
- | - | - | - | |
05 | 2.2437: Recover waste heat from equipment | $1,705 | $2,850 | - | - |
$1,705
-
MMBtu
|
- | - | |
06 | 2.2523: Reduce infiltration to refrigerated areas; isolate hot equipment from refrigerated areas | $2,994 | $2,830 | - | - |
$2,994
-
MMBtu
|
- | - | |
07 | 2.7124: Make a practice of turning off lights when not needed | $6,431 | $1,520 | - | - |
$6,431
-
MMBtu
|
- | - | |
08 | 2.2511: Insulate bare equipment | $127 | $159 |
$127
2,931
kWh
|
- | - | - | - | |
09 | 2.2514: Cover open tanks | $937 | $188 | - |
$492
-
kW-mo/yr
|
$445
-
MMBtu
|
- | - | |
10 | 3.5311: Recover and reuse waste material | $6,250 | $500 | - | - | - |
$6,250
-
lb
|
- | |
11 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $1,000 | $150 | - | - | - |
$1,000
-
lb
|
- | |
12 | 2.3132: Recharge batteries on during off-peak demand periods | $338 | $147 | - | - | - | - | $338 | |
TOTAL RECOMMENDED | $47,389 | $15,423 |
$18,815
418,230
kWh
|
$9,411
-
kW-mo/yr
|
$11,575
-
MMBtu
|
$7,250
-
lb
|
$338 | ||
TOTAL IMPLEMENTED | $5,491 | $4,290 |
$1,437
31,946
kWh
|
$566
-
kW-mo/yr
|
$2,150
-
MMBtu
|
$1,000
-
lb
|
$338 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs