| Assessment Year | 1996 |
|---|---|
| Principal Product | Printed Paper Products |
| NAICS |
n/a
|
| SIC | 2679: Converted Paper and Paperboard Products, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
140,000
ft2
|
| Annual Production | 17,000,000
lb
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $88,674 | 2,031,946 |
kWh
|
$0.044 |
| Electricity Demand | $48,707 | 5,286 |
kW-mo/yr
|
$9.21 |
| Electricity Fees | $3,460 | - |
|
- |
| Natural Gas | $21,825 | 4,215 |
MMBtu
|
$5.18 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $16,753 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,418 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $90 | $31 |
$66
1,465
kWh
|
$24
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,307 | $270 |
$1,307
30,188
kWh
|
- | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,462 | $200 |
$1,462
33,705
kWh
|
- | - | - | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $4,678 | $11,375 | - | - | - |
$4,678
-
MMBtu
|
- | |
| 05 | 2.7135: Install occupancy sensors | $245 | $94 |
$245
4,396
kWh
|
- | - | - | - | |
| 06 | 2.3212: Optimize plant power factor | $657 | $1,760 | - | - | $657 | - | - | |
| 07 | 2.2447: Heat water with exhaust heat | $5,214 | $3,300 |
$253
5,862
kWh
|
$82
-
kW-mo/yr
|
- |
$4,879
-
MMBtu
|
- | |
| 08 | 3.5313: Increase amount of waste recovered for resale | $3,100 | - | - | - | - | - |
$3,100
-
lb
|
|
| TOTAL RECOMMENDED | $16,753 | $17,030 |
$3,333
75,616
kWh
|
$106
-
kW-mo/yr
|
$657 |
$9,557
-
MMBtu
|
$3,100
-
lb
|
||
| TOTAL IMPLEMENTED | $11,418 | $3,895 |
$3,333
75,616
kWh
|
$106
-
kW-mo/yr
|
- |
$4,879
-
MMBtu
|
$3,100
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs