ITAC Assessment: MS0278
ITAC logo
ITAC Assessment: MS0278
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Steel Machining/Assembly
NAICS 332312: Fabricated Structural Metal Manufacturing
SIC 3441: Fabricated Structural Metal
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 125,000
ft2
Annual Production 60,000
pieces
Production Hrs. Annual 4,080
hrs
Location (State) Mississippi

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $99,278 2,105,326
kWh
Electricity Demand $26,254 8,288
kW-mo/yr
Electricity Fees $53,426 -
Natural Gas $104,828 10,663
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $36,000 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $10,687

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $21,255 $21,983 $12,570
277,083
kWh
$2,545
-
kW-mo/yr
$6,140 -
02 2.2511: Insulate bare equipment $8,073 $710 - - - $8,073
-
MMBtu
03 2.7124: Make a practice of turning off lights when not needed $3,012 $34 $1,799
39,658
kWh
$339
-
kW-mo/yr
$874 -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,614 $228 $1,809
39,882
kWh
- $805 -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $795 $2,627 $475
10,466
kWh
$90
-
kW-mo/yr
$230 -
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $251 $358 $125
2,762
kWh
$58
-
kW-mo/yr
$68 -
TOTAL RECOMMENDED $36,000 $25,940 $16,778
369,851
kWh
$3,032
-
kW-mo/yr
$8,117 $8,073
-
MMBtu
TOTAL IMPLEMENTED $10,687 $938 $1,809
39,882
kWh
- $805 $8,073
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs