ITAC Assessment: NV0060
ITAC logo
ITAC Assessment: NV0060
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Commercial Printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area
n/a
Annual Production 1,000,000
lb
Production Hrs. Annual 8,580
hrs
Location (State) California

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $172,678 2,961,606
kWh
Electricity Demand $54,613 7,219
kW-mo/yr
Electricity Fees $528 -
Natural Gas $72,826 12,387
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $17,307 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $4,501

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.4221: Install compressor air intakes in coolest locations $1,882 $305 $1,882
32,239
kWh
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,819 $300 $1,819
31,067
kWh
- -
03 2.7111: Reduce illumination to minimum necessary levels $9,371 $1,575 $7,492
129,250
kWh
$1,879
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $3,435 $556 $3,435
58,910
kWh
- -
05 3.5316: Contract a wood pallet recycling company $800 - - - $800
TOTAL RECOMMENDED $17,307 $2,736 $14,628
251,466
kWh
$1,879
-
kW-mo/yr
$800
TOTAL IMPLEMENTED $4,501 $605 $3,701
63,306
kWh
- $800
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs