Assessment Year | 1996 |
---|---|
Principal Product | custom compounded plastic resins |
NAICS |
n/a
|
SIC | 3087: Custom Compounding of Purchased Plastics Resins |
Sales Range | $10 M to 50M |
# of Employees | 50 |
Plant Area |
60,000
ft2
|
Annual Production | 7,000,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $121,521 | 2,700,762 |
kWh
|
$0.045 |
Electricity Demand | $61,316 | 7,795 |
kW-mo/yr
|
$7.87 |
Electricity Fees | $5,463 | - |
|
- |
Natural Gas | $12,488 | 2,207 |
MMBtu
|
$5.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $13,816 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,694 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $1,263 | $3,525 | - | - | $1,263 | - | - | |
02 | 2.7243: Improve air circulation with destratification fans / other methods | $1,698 | $4,225 | - | - | - |
$1,698
-
MMBtu
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $7,602 | $21,840 |
$4,951
109,906
kWh
|
$2,651
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $513 | $260 |
$513
11,430
kWh
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,300 | $600 |
$1,300
29,015
kWh
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $438 | $100 |
$438
9,965
kWh
|
- | - | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $394 | $25 |
$281
7,620
kWh
|
$113
-
kW-mo/yr
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $503 | $164 |
$423
9,379
kWh
|
$80
-
kW-mo/yr
|
- | - | - | |
09 | 3.5313: Increase amount of waste recovered for resale | $105 | $30 | - | - | - | - |
$105
-
lb
|
|
TOTAL RECOMMENDED | $13,816 | $30,769 |
$7,906
177,315
kWh
|
$2,844
-
kW-mo/yr
|
$1,263 |
$1,698
-
MMBtu
|
$105
-
lb
|
||
TOTAL IMPLEMENTED | $1,694 | $625 |
$1,581
36,635
kWh
|
$113
-
kW-mo/yr
|
- | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs