ITAC Assessment: NV0032
ITAC logo
ITAC Assessment: NV0032
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Motorcycle Parts
NAICS
n/a
SIC 3751: Motorcycles, Bicycles, and Parts
Sales Range $1
M
to 5
M
# of Employees 110
Plant Area 77,200
ft2
Annual Production 120,000
pieces
Production Hrs. Annual 4,420
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,004 558,617
kWh
Natural Gas $26,063 4,380
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $7,868 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $931

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $640 $3,211 $640
6,155
kWh
-
02 2.4231: Reduce the pressure of compressed air to the minimum required $291 - $291
3,224
kWh
-
03 2.4221: Install compressor air intakes in coolest locations $289 $400 $289
2,638
kWh
-
04 2.2511: Insulate bare equipment $3,702 $1,741 - $3,702
-
MMBtu
05 2.2511: Insulate bare equipment $2,946 $2,937 - $2,946
-
MMBtu
TOTAL RECOMMENDED $7,868 $8,289 $1,220
12,017
kWh
$6,648
-
MMBtu
TOTAL IMPLEMENTED $931 $3,211 $931
9,379
kWh
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs