| Assessment Year | 1995 |
|---|---|
| Principal Product | Injection Molded Pipe Brackets and Steel Braided Hose |
| NAICS |
n/a
|
| SIC | 3089: Plastics Products, Not Elsewhere Classified |
| Sales Range | $5 M to 10M |
| # of Employees | 100 |
| Plant Area |
67,000
ft2
|
| Annual Production | 3,000,000
pieces
|
| Production Hrs. Annual | 4,160
hrs
|
| Location (State) | Nevada |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $176,832 | 2,541,325 |
kWh
|
$0.070 |
| Natural Gas | $27,586 | 4,756 |
MMBtu
|
$5.80 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $20,747 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $13,330 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $1,350 | $3,190 |
$1,350
23,447
kWh
|
- | |
| 02 | 2.7135: Install occupancy sensors | $433 | $327 |
$433
8,206
kWh
|
- | |
| 03 | 2.7243: Improve air circulation with destratification fans / other methods | $2,745 | $5,526 | - |
$2,745
-
MMBtu
|
|
| 04 | 2.7446: Utilize sensors controlling roof and wall openings | $875 | $888 | - |
$875
-
MMBtu
|
|
| 05 | 2.7447: Install vinyl strip / high speed / air curtain doors | $2,424 | $3,622 | - |
$2,424
-
MMBtu
|
|
| 06 | 2.6218: Turn off equipment when not in use | $6,798 | - |
$6,798
143,904
kWh
|
- | |
| 07 | 2.2511: Insulate bare equipment | $3,364 | $1,444 |
$3,364
71,219
kWh
|
- | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,776 | - |
$1,776
37,515
kWh
|
- | |
| 09 | 2.3212: Optimize plant power factor | $982 | $3,382 |
$982
-
kWh
|
- | |
| TOTAL RECOMMENDED | $20,747 | $18,379 |
$14,703
284,291
kWh
|
$6,044
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $13,330 | $10,194 |
$10,906
204,866
kWh
|
$2,424
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs