ITAC Assessment: NV0016
ITAC logo
ITAC Assessment: NV0016
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1995
Principal Product Vinyl Sheeting
NAICS
n/a
SIC 3081: Unsupported Plastics Film and Sheet
Sales Range $10
M
to 50
M
# of Employees 121
Plant Area 24,000
ft2
Annual Production 21,000,000
lb
Production Hrs. Annual 8,736
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $387,368 6,187,280
kWh
Natural Gas $175,023 32,507
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $33,056 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.4133: Use most efficient type of electric motors $4,667 $6,209 $4,667
74,443
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $326 $285 $326
5,275
kWh
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $875 $120 $875
14,068
kWh
-
04 2.2136: Install / repair insulation on steam lines $6,488 $1,744 - $6,488
-
MMBtu
05 2.2511: Insulate bare equipment $10,116 $3,439 - $10,116
-
MMBtu
06 2.1233: Analyze flue gas for proper air/fuel ratio $6,870 $1,000 - $6,870
-
MMBtu
07 2.7142: Utilize higher efficiency lamps and/or ballasts $2,507 $792 $2,507
39,859
kWh
-
08 2.3212: Optimize plant power factor $1,207 $900 $1,207
-
kWh
-
TOTAL RECOMMENDED $33,056 $14,489 $9,582
133,645
kWh
$23,474
-
MMBtu
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs