ITAC Assessment: NV0007
ITAC logo
ITAC Assessment: NV0007
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1994
Principal Product Plastic Food Containers
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 45
Plant Area 120,000
ft2
Annual Production 3,000,000
lb
Production Hrs. Annual 7,500
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $354,813 5,116,061
kWh
Natural Gas $19,557 3,833
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $14,782 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,368

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Administrative Changes Savings
01 2.4133: Use most efficient type of electric motors $8,001 $3,784 $8,001
115,475
kWh
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $2,561 $815 $2,561
36,928
kWh
-
03 2.7111: Reduce illumination to minimum necessary levels $366 $20 $366
5,275
kWh
-
04 2.2511: Insulate bare equipment $61 $31 $61
879
kWh
-
05 2.4221: Install compressor air intakes in coolest locations $1,382 $880 $1,382
19,930
kWh
-
06 2.3212: Optimize plant power factor $1,970 $6,450 $1,970
-
kWh
-
07 2.8123: Pay utility bills on time $441 - - $441
TOTAL RECOMMENDED $14,782 $11,980 $14,341
178,487
kWh
$441
TOTAL IMPLEMENTED $3,368 $835 $2,927
42,203
kWh
$441
Yearly Savings* Imp'd Cost* Electricity Usage Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs