Assessment Year | 2025 |
---|---|
Principal Product | aggregate,ready mixed concrete,cement,Asphalt |
NAICS | 212319: Other Crushed and Broken Stone Mining and Quarrying |
SIC | 1429: Crushed and Broken Stone, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 130 |
Plant Area |
138,830,000
ft2
|
Annual Production | 7,500,000
ton
|
Production Hrs. Annual | 7,260
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,242,366 | 36,249,600 |
kWh
|
$0.062 |
Electricity Demand | $1,041,798 | 110,130 |
kW-mo/yr
|
$9.46 |
Electricity Fees | $132,127 | - |
|
- |
TOTAL YEARLY COSTS | $3,416,292 | |||
RECOMMENDED SAVINGS* | $386,564 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,253 | $5,609 |
$4,992
80,651
kWh
|
$1,261
-
kW-mo/yr
|
- | - | |
02 | 2.4224: Upgrade controls on compressors | $13,920 | $30,800 | - | - | $13,920 | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $724 | $950 |
$724
11,697
kWh
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $65,667 | $138,252 |
$46,514
751,433
kWh
|
$19,153
-
kW-mo/yr
|
- | - | |
05 | 4.431: Train operators for maximum operating efficiency | $150,000 | $100,000 | - | - | - | $150,000 | |
06 | 4.611: Begin a practice of predictive / preventative maintenance | $150,000 | $9,690 | - | - | - | $150,000 | |
TOTAL RECOMMENDED | $386,564 | $285,301 |
$52,230
843,780
kWh
|
$20,414
-
kW-mo/yr
|
$13,920 | $300,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs