Assessment Year | 2025 |
---|---|
Principal Product | Circuit Boards |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
40,000
ft2
|
Annual Production | 3,000
units
|
Production Hrs. Annual | 4,432
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $42,716 | 983,116 |
kWh
|
$0.043 | |
Electricity Demand | $43,442 | 4,313 |
kW-mo/yr
|
$10.07 | |
Electricity Fees | $13,097 | - |
|
- | |
Natural Gas | $4,621 | 266 |
MMBtu
|
$17.39 | |
Waste Disposal Costs | |||||
Water Usage | $6,000 | 3,000 |
Tgal
|
$2.00 | |
TOTAL YEARLY COSTS | $109,875 | ||||
RECOMMENDED SAVINGS* | $165,382 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,097 | $5,609 |
$1,903
43,798
kWh
|
$1,194
-
kW-mo/yr
|
- | - | |
02 | 2.6232: Install set-back timers | $1,025 | - |
$1,025
23,599
kWh
|
- | - | - | |
03 | 4.445: Install equipment to move product | $150,000 | $182,000 | - | - | - | $150,000 | |
04 | 2.3212: Optimize plant power factor | $3,340 | $18,058 | - |
$3,340
-
kW-mo/yr
|
- | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $7,920 | $5,000 | - | - | $7,920 | - | |
TOTAL RECOMMENDED | $165,382 | $210,666 |
$2,928
67,397
kWh
|
$4,534
-
kW-mo/yr
|
$7,920 | $150,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs