| Assessment Year | 2024 |
|---|---|
| Principal Product | Structural steel beams |
| NAICS | 332312: Fabricated Structural Metal Manufacturing |
| SIC | 3441: Fabricated Structural Metal |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
30,000
ft2
|
| Annual Production | 7,500
ton
|
| Production Hrs. Annual | 2,080
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $59,607 | 748,200 |
kWh
|
$0.080 | |
| Electricity Demand | $54,804 | 4,770 |
kW-mo/yr
|
$11.49 | |
| Electricity Fees | $7,499 | - |
|
- | |
| Waste Disposal Costs | |||||
| Water Usage | $1,000 | 73 |
Tgal
|
$13.70 | |
| TOTAL YEARLY COSTS | $122,909 | ||||
| RECOMMENDED SAVINGS* | $161,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $10,502 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,196 | $5,609 |
$1,205
15,122
kWh
|
$991
-
kW-mo/yr
|
- | - | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $954 | - |
$524
6,571
kWh
|
$431
-
kW-mo/yr
|
- | - | |
| 03 | 2.4222: Install adequate dryers on air lines to eliminate blowdown | $1,000 | $5,300 | - | - | - | $1,000 | |
| 04 | 2.4226: Use / purchase optimum sized compressor | $150,000 | $38,900 | - | - | - | $150,000 | |
| 05 | 4.812: Apply for investment incentives | $7,352 | $5,000 | - | - | $7,352 | - | |
| TOTAL RECOMMENDED | $161,502 | $54,809 |
$1,729
21,693
kWh
|
$1,422
-
kW-mo/yr
|
$7,352 | $151,000 | ||
| TOTAL IMPLEMENTED | $10,502 | $10,609 |
$1,729
21,693
kWh
|
$1,422
-
kW-mo/yr
|
$7,352 | - | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs