ITAC Assessment: NL0131
ITAC logo
ITAC Assessment: NL0131
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2026
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range $1
M
to 5
M
# of Employees 3
Plant Area 49,935
ft2
Annual Production 474,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $114,700 1,674,450
kWh
Electricity Demand $49,232 3,077
kW-mo/yr
Natural Gas $15,555 5,717
MMBtu
Fuel Oil #2 $5,073 207
MMBtu
Waste Disposal Costs
Water Usage $3,367 1,878
Tgal
TOTAL YEARLY COSTS $187,927
RECOMMENDED SAVINGS* $57,164 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Ancillary Material Cost Savings
01 2.4131: Size electric motors for peak operating efficiency $54,053 $4,639 $809
11,725
kWh
- $305
-
MMBtu
$52,939
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,787 $3,355 $394
5,706
kWh
$1,394
-
kW-mo/yr
- -
03 2.4111: Utilize energy-efficient belts and other improved mechanisms $818 $335 $622
9,009
kWh
$197
-
kW-mo/yr
- -
04 2.7444: Close holes and openings in building such as broken windows $274 $172 $274
3,974
kWh
- - -
05 2.6218: Turn off equipment when not in use $118 $35 $93
1,340
kWh
$26
-
kW-mo/yr
- -
06 2.4231: Reduce the pressure of compressed air to the minimum required $113 $35 $113
1,633
kWh
- - -
TOTAL RECOMMENDED $57,164 $8,571 $2,304
33,387
kWh
$1,616
-
kW-mo/yr
$305
-
MMBtu
$52,939
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Fuel Oil #2 Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs