ITAC Assessment: NL0121
ITAC logo
ITAC Assessment: NL0121
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product Concrete Pipe Machinery
NAICS 333249: Other Industrial Machinery Manufacturing
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 96,500
ft2
Annual Production 50,000
units
Production Hrs. Annual 2,500
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $60,105 994,368
kWh
Electricity Demand $15,096 2,434
kW-mo/yr
Electricity Fees $13,205 -
Natural Gas $30,264 5,109
MMBtu
LPG $11,875 716
MMBtu
Other Gas $3,420 1
MMBtu
Waste Disposal Costs
Water Usage $1,298 105
Tgal
Water Disposal $1,628 105
Tgal
Other Liquid (non-haz) $2,404 1
gal
TOTAL YEARLY COSTS $139,295
RECOMMENDED SAVINGS* $113,431 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
01 2.4321: Upgrade obsolete equipment $90,884 $425,000 - - - - - - $15,884 $75,000
02 2.7231: Use radiant heater for spot heating $10,375 $11,349 $13,968
232,800
kWh
$1,633
-
kW-mo/yr
- $(-5,226.0)
-
MMBtu
- - - -
03 3.2121: Convert to electrostatic powder coating $8,794 $54,473 - - - - - - $8,794 -
04 2.8121: Apply for tax-free status for energy purchases $1,480 $6,250 - - $1,480 - - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $805 $1,400 $1,405
23,422
kWh
- - - $(-500.0) $(-100.0) - -
06 2.4221: Install compressor air intakes in coolest locations $481 $1,785 $481
8,010
kWh
- - - - - - -
07 2.6218: Turn off equipment when not in use $355 $63 $355
5,919
kWh
- - - - - - -
08 2.4111: Utilize energy-efficient belts and other improved mechanisms $257 $1,558 $186
3,103
kWh
$71
-
kW-mo/yr
- - - - - -
TOTAL RECOMMENDED $113,431 $501,878 $16,395
273,254
kWh
$1,704
-
kW-mo/yr
$1,480 $(-5,226.0)
-
MMBtu
$(-500.0) $(-100.0) $24,678 $75,000
TOTAL IMPLEMENTED - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs