Assessment Year | 2021 |
---|---|
Principal Product | Water Treatment |
NAICS | 237110: Water and Sewer Line and Related Structures Construction |
SIC | 1623: Water, Sewer, Pipeline, and Communications and Power Line Construction |
Sales Range | $10 M to 50M |
# of Employees | 42 |
Plant Area |
260,000
ft2
|
Annual Production | 1,500
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $87,218 | 2,409,300 |
kWh
|
$0.036 |
Electricity Demand | $65,464 | 3,968 |
kW-mo/yr
|
$16.50 |
Electricity Fees | $3,405 | - |
|
- |
Natural Gas | $51,309 | 8,499 |
MMBtu
|
$6.04 |
Other Gas | $26,561 | 1,058 |
MMBtu
|
$25.10 |
TOTAL YEARLY COSTS | $233,958 | |||
RECOMMENDED SAVINGS* | $34,592 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,096 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.8222: Size trucks to job | $14,756 | $56,000 | - | - | - |
$14,756
-
MMBtu
|
- | |
02 | 2.8114: Change rate schedules or other changes in utility service | $14,084 | $14,000 | - | - | - | - | $14,084 | |
03 | 2.7135: Install occupancy sensors | $2,075 | $2,348 |
$2,075
57,318
kWh
|
- | - | - | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,665 | $1,000 |
$1,032
28,499
kWh
|
$633
-
kW-mo/yr
|
- | - | - | |
05 | 2.7221: Lower temperature during the winter season and vice-versa | $1,609 | $100 | - | - |
$1,609
-
MMBtu
|
- | - | |
06 | 2.7221: Lower temperature during the winter season and vice-versa | $403 | $100 |
$8
225
kWh
|
- |
$395
-
MMBtu
|
- | - | |
TOTAL RECOMMENDED | $34,592 | $73,548 |
$3,115
86,042
kWh
|
$633
-
kW-mo/yr
|
$2,004
-
MMBtu
|
$14,756
-
MMBtu
|
$14,084 | ||
TOTAL IMPLEMENTED | $16,096 | $14,200 |
$8
225
kWh
|
- |
$2,004
-
MMBtu
|
- | $14,084 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs