ITAC Assessment: UU0189
ITAC logo
ITAC Assessment: UU0189
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Water Treatment
NAICS 237110: Water and Sewer Line and Related Structures Construction
SIC 1623: Water, Sewer, Pipeline, and Communications and Power Line Construction
Sales Range $10
M
to 50
M
# of Employees 42
Plant Area 260,000
ft2
Annual Production 1,500
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Utah

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $87,218 2,409,300
kWh
Electricity Demand $65,464 3,968
kW-mo/yr
Electricity Fees $3,405 -
Natural Gas $51,309 8,499
MMBtu
Other Gas $26,561 1,058
MMBtu
TOTAL YEARLY COSTS $233,958
RECOMMENDED SAVINGS* $34,592 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,096

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Personnel Changes Savings
01 2.8222: Size trucks to job $14,756 $56,000 - - - $14,756
-
MMBtu
-
02 2.8114: Change rate schedules or other changes in utility service $14,084 $14,000 - - - - $14,084
03 2.7135: Install occupancy sensors $2,075 $2,348 $2,075
57,318
kWh
- - - -
04 2.4231: Reduce the pressure of compressed air to the minimum required $1,665 $1,000 $1,032
28,499
kWh
$633
-
kW-mo/yr
- - -
05 2.7221: Lower temperature during the winter season and vice-versa $1,609 $100 - - $1,609
-
MMBtu
- -
06 2.7221: Lower temperature during the winter season and vice-versa $403 $100 $8
225
kWh
- $395
-
MMBtu
- -
TOTAL RECOMMENDED $34,592 $73,548 $3,115
86,042
kWh
$633
-
kW-mo/yr
$2,004
-
MMBtu
$14,756
-
MMBtu
$14,084
TOTAL IMPLEMENTED $16,096 $14,200 $8
225
kWh
- $2,004
-
MMBtu
- $14,084
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs