Assessment Year | 2025 |
---|---|
Principal Product | Lottery Tickets |
NAICS | 323111: Commercial Printing (except Screen and Books) |
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
129,940
ft2
|
Annual Production | 2,400,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Iowa |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $170,559 | 2,788,700 |
kWh
|
$0.061 | |
Electricity Demand | $39,601 | 7,131 |
kW-mo/yr
|
$5.55 | |
Electricity Fees | $9,594 | - |
|
- | |
Natural Gas | $9,869 | 1,350 |
MMBtu
|
$7.31 | |
Other Gas | $384 | 1 |
MMBtu
|
$384.00 | |
Waste Disposal Costs | |||||
Water Usage | $4,155 | 1,005 |
Tgal
|
$4.13 | |
Water Disposal | $6,164 | 1,005 |
Tgal
|
$6.13 | |
Other Liquid (non-haz) | $681 | 1 |
gal
|
$681.00 | |
TOTAL YEARLY COSTS | $241,007 | ||||
RECOMMENDED SAVINGS* | $21,364 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,202 | $125 |
$10,102
165,610
kWh
|
- | - | $(-800.0) | $(-100.0) | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,713 | $5,826 |
$3,241
53,127
kWh
|
$567
-
kW-mo/yr
|
- | $905 | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $2,899 | $2,000 | - | - | $2,899 | - | - | |
04 | 2.4224: Upgrade controls on compressors | $2,086 | $675 |
$2,086
34,193
kWh
|
- | - | - | - | |
05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,863 | $25 | - |
$1,863
-
kW-mo/yr
|
- | - | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $398 | $100 |
$398
6,530
kWh
|
- | - | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $203 | $303 |
$83
1,367
kWh
|
$11
-
kW-mo/yr
|
- | $109 | - | |
TOTAL RECOMMENDED | $21,364 | $9,054 |
$15,910
260,827
kWh
|
$2,441
-
kW-mo/yr
|
$2,899 | $214 | $(-100.0) | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs