Assessment Year | 2024 |
---|---|
Principal Product | Metal Plating |
NAICS | 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers |
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $10 M to 50M |
# of Employees | 60 |
Plant Area |
85,000
ft2
|
Annual Production | 175,000
units
|
Production Hrs. Annual | 2,000
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $65,497 | 2,053,800 |
kWh
|
$0.032 | |
Electricity Demand | $87,798 | 5,632 |
kW-mo/yr
|
$15.59 | |
Electricity Fees | $7,328 | - |
|
- | |
Natural Gas | $147,383 | 23,742 |
MMBtu
|
$6.21 | |
Other Gas | $3,856 | 1 |
MMBtu
|
$3,856.00 | |
Waste Disposal Costs | |||||
Water Usage | $7,682 | 2,418 |
Tgal
|
$3.18 | |
Water Disposal | $7,888 | 2,418 |
Tgal
|
$3.26 | |
Other Liquid (non-haz) | $1,897 | 1 |
gal
|
$1,897.00 | |
TOTAL YEARLY COSTS | $329,329 | ||||
RECOMMENDED SAVINGS* | $128,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4321: Upgrade obsolete equipment | $88,713 | $315,000 |
$(-1,777.0)
(-55,902)
kWh
|
- | - | - | - | - | $5,875 | - | $84,615 | - | - | |
02 | 2.7444: Close holes and openings in building such as broken windows | $21,177 | $6,200 | - | - | - |
$177
-
MMBtu
|
- | - | - | - | - | $21,000 | - | |
03 | 2.8121: Apply for tax-free status for energy purchases | $10,283 | $250 | - | - | $6,427 | - |
$3,856
-
MMBtu
|
- | - | - | - | - | - | |
04 | 2.7243: Improve air circulation with destratification fans / other methods | $5,253 | $10,118 |
$198
6,233
kWh
|
$555
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | $4,500 | |
05 | 2.8117: Install sub-metering equipment | $1,237 | $1,850 | - | - | - | - | - |
$1,237
-
Tgal
|
- | - | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,130 | $1,000 |
$1,380
43,413
kWh
|
- | - | - | - | - | $(-150.0) | $(-100.0) | - | - | - | |
07 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $882 | $802 |
$300
9,460
kWh
|
$582
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | - | |
TOTAL RECOMMENDED | $128,675 | $335,220 |
$101
3,204
kWh
|
$1,137
-
kW-mo/yr
|
$6,427 |
$177
-
MMBtu
|
$3,856
-
MMBtu
|
$1,237
-
Tgal
|
$5,725 | $(-100.0) | $84,615 | $21,000 | $4,500 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Gas Savings | Water Disposal Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | Primary Product Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs