ITAC Assessment: NL0102
ITAC logo
ITAC Assessment: NL0102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Metal Plating
NAICS 332812: Metal Coating, Engraving (except Jewelry and Silverware), and Allied Services to Manufacturers
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 85,000
ft2
Annual Production 175,000
units
Production Hrs. Annual 2,000
hrs
Location (State) Nebraska

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $65,497 2,053,800
kWh
Electricity Demand $87,798 5,632
kW-mo/yr
Electricity Fees $7,328 -
Natural Gas $147,383 23,742
MMBtu
Other Gas $3,856 1
MMBtu
Waste Disposal Costs
Water Usage $7,682 2,418
Tgal
Water Disposal $7,888 2,418
Tgal
Other Liquid (non-haz) $1,897 1
gal
TOTAL YEARLY COSTS $329,329
RECOMMENDED SAVINGS* $128,675 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings Increase in Production Savings
01 2.4321: Upgrade obsolete equipment $88,713 $315,000 $(-1,777.0)
(-55,902)
kWh
- - - - - $5,875 - $84,615 - -
02 2.7444: Close holes and openings in building such as broken windows $21,177 $6,200 - - - $177
-
MMBtu
- - - - - $21,000 -
03 2.8121: Apply for tax-free status for energy purchases $10,283 $250 - - $6,427 - $3,856
-
MMBtu
- - - - - -
04 2.7243: Improve air circulation with destratification fans / other methods $5,253 $10,118 $198
6,233
kWh
$555
-
kW-mo/yr
- - - - - - - - $4,500
05 2.8117: Install sub-metering equipment $1,237 $1,850 - - - - - $1,237
-
Tgal
- - - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,130 $1,000 $1,380
43,413
kWh
- - - - - $(-150.0) $(-100.0) - - -
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $882 $802 $300
9,460
kWh
$582
-
kW-mo/yr
- - - - - - - - -
TOTAL RECOMMENDED $128,675 $335,220 $101
3,204
kWh
$1,137
-
kW-mo/yr
$6,427 $177
-
MMBtu
$3,856
-
MMBtu
$1,237
-
Tgal
$5,725 $(-100.0) $84,615 $21,000 $4,500
TOTAL IMPLEMENTED - - - - - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Other Gas Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings Primary Product Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs