| Assessment Year | 2023 |
|---|---|
| Principal Product | Pet Food Cans |
| NAICS | 332431: Metal Can Manufacturing |
| SIC | 3411: Metal Cans |
| Sales Range | $50 M to 100M |
| # of Employees | 179 |
| Plant Area |
500,300
ft2
|
| Annual Production | 500,000,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Iowa |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $800,202 | 18,491,595 |
kWh
|
$0.043 | |
| Electricity Demand | $134,129 | 28,814 |
kW-mo/yr
|
$4.65 | |
| Electricity Fees | $177,929 | - |
|
- | |
| Natural Gas | $220,147 | 30,435 |
MMBtu
|
$7.23 | |
| Waste Disposal Costs | |||||
| Water Usage | $7,508 | 684 |
Tgal
|
$10.98 | |
| TOTAL YEARLY COSTS | $1,339,915 | ||||
| RECOMMENDED SAVINGS* | $97,578 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $20,788 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.4239: Eliminate or reduce compressed air usage | $42,345 | $20,000 |
$36,875
857,558
kWh
|
$5,470
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.2437: Recover waste heat from equipment | $24,481 | $25,000 | - | - |
$24,481
-
MMBtu
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,256 | $4,500 |
$10,916
253,869
kWh
|
- | - | $(-560.0) | $(-100.0) | |
| 04 | 2.4221: Install compressor air intakes in coolest locations | $7,880 | $12,650 |
$7,880
183,254
kWh
|
- | - | - | - | |
| 05 | 2.4239: Eliminate or reduce compressed air usage | $6,194 | $140 |
$6,194
144,027
kWh
|
- | - | - | - | |
| 06 | 2.1131: Repair faulty insulation in furnaces, boilers, etc | $4,338 | $7,210 | - | - |
$4,338
-
MMBtu
|
- | - | |
| 07 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,084 | $35 | - |
$2,084
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $97,578 | $69,535 |
$61,865
1,438,708
kWh
|
$7,554
-
kW-mo/yr
|
$28,819
-
MMBtu
|
$(-560.0) | $(-100.0) | ||
| TOTAL IMPLEMENTED | $20,788 | $11,850 |
$17,110
397,896
kWh
|
- |
$4,338
-
MMBtu
|
$(-560.0) | $(-100.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs