ITAC Assessment: NL0070
ITAC logo
ITAC Assessment: NL0070
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Commercial Doors
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $100
M
to 500
M
# of Employees 650
Plant Area 373,000
ft2
Annual Production 400,000
units
Production Hrs. Annual 7,509
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $401,137 10,355,851
kWh
Electricity Demand $514,237 21,997
kW-mo/yr
Natural Gas $248,498 43,718
MMBtu
Waste Disposal Costs
Water Usage $32,441 9,984
Tgal
Water Disposal $33,775 9,984
Tgal
TOTAL YEARLY COSTS $1,230,088
RECOMMENDED SAVINGS* $115,608 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $63,735

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7231: Use radiant heater for spot heating $41,224 $20,136 - - $41,224
-
MMBtu
- -
02 2.4224: Upgrade controls on compressors $32,832 $16,500 $15,952
409,028
kWh
$16,880
-
kW-mo/yr
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $26,148 $35 - $26,148
-
kW-mo/yr
- - -
04 2.7228: Avoid introducing hot, humid, or dirty air into hvac system $6,619 $1,180 $2,060
52,813
kWh
$4,559
-
kW-mo/yr
- - -
05 2.4221: Install compressor air intakes in coolest locations $4,030 $4,945 $4,030
103,338
kWh
- - - -
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,590 $23,500 $4,250
108,967
kWh
- - $(-560.0) $(-100.0)
07 2.4111: Utilize energy-efficient belts and other improved mechanisms $675 $3,315 $317
8,138
kWh
$358
-
kW-mo/yr
- - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $490 $854 $123
3,154
kWh
$101
-
kW-mo/yr
- $266 -
TOTAL RECOMMENDED $115,608 $70,465 $26,732
685,438
kWh
$48,046
-
kW-mo/yr
$41,224
-
MMBtu
$(-294.0) $(-100.0)
TOTAL IMPLEMENTED $63,735 $44,204 $20,642
529,287
kWh
$43,487
-
kW-mo/yr
- $(-294.0) $(-100.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs