ITAC Assessment: NL0064
ITAC logo
ITAC Assessment: NL0064
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product Sliced Bacon
NAICS 311612: Meat Processed from Carcasses
SIC 2013: Sausages and Other Prepared Meat Products
Sales Range greater than $500
M
# of Employees 225
Plant Area 110,000
ft2
Annual Production 120,000,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Iowa

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $313,279 9,394,238
kWh
Electricity Demand $192,285 16,328
kW-mo/yr
Electricity Fees $2,955 -
Natural Gas $161,842 32,648
MMBtu
Waste Disposal Costs
Water Usage $54,116 23,010
Tgal
Water Disposal $175,799 20,836
Tgal
TOTAL YEARLY COSTS $900,276
RECOMMENDED SAVINGS* $83,244 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $83,244

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Water Usage Savings One-time Revenue or Avoided Cost Savings
01 3.3123: Use decanting, flotation to remove contaminants $79,442 $292,000 - - - $79,442
02 2.2511: Insulate bare equipment $1,251 $1,729 $1,251
37,909
kWh
- - -
03 2.4221: Install compressor air intakes in coolest locations $1,248 $2,875 $1,248
37,829
kWh
- - -
04 3.7193: Use high pressure wash systems $768 $240 - $298
-
MMBtu
$207
-
Tgal
$263
05 2.8114: Change rate schedules or other changes in utility service $331 $90 - - - $331
06 2.2511: Insulate bare equipment $204 $130 - $204
-
MMBtu
- -
TOTAL RECOMMENDED $83,244 $297,064 $2,499
75,738
kWh
$502
-
MMBtu
$207
-
Tgal
$80,036
TOTAL IMPLEMENTED $83,244 $297,064 $2,499
75,738
kWh
$502
-
MMBtu
$207
-
Tgal
$80,036
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Water Usage Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs