Assessment Year | 2019 |
---|---|
Principal Product | Rubber Stoppers |
NAICS | 325412: Pharmaceutical Preparation Manufacturing |
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
100,000
ft2
|
Annual Production | 8,000,000,000
units
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Nebraska |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $368,666 | 9,393,184 |
kWh
|
$0.039 | |
Electricity Demand | $397,488 | 18,928 |
kW-mo/yr
|
$21.00 | |
Natural Gas | $163,199 | 45,046 |
MMBtu
|
$3.62 | |
Waste Disposal Costs | |||||
Water Usage | $801 | 290 |
Tgal
|
$2.76 | |
Water Disposal | $31,257 | 10,859 |
Tgal
|
$2.88 | |
TOTAL YEARLY COSTS | $961,411 | ||||
RECOMMENDED SAVINGS* | $271,828 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $269,210 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7232: Replace existing hvac unit with high efficiency model | $238,833 | $700,000 |
$109,041
2,726,016
kWh
|
$124,992
-
kW-mo/yr
|
- | - | $4,800 | - | - | |
02 | 2.3212: Optimize plant power factor | $10,636 | $52,000 | - | - | $10,636 | - | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $6,751 | $600 |
$7,011
173,907
kWh
|
- | - | - | $(-160.0) | $(-100.0) | - | |
04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,670 | $100 | - |
$5,670
-
kW-mo/yr
|
- | - | - | - | - | |
05 | 2.7444: Close holes and openings in building such as broken windows | $5,000 | $19,750 | - | - | - | - | - | - | $5,000 | |
06 | 3.5314: Use in-process recycling whenever possible | $2,618 | $3,180 | - | - | - | - | $148 | $2,470 | - | |
07 | 2.2135: Repair and eliminate steam leaks | $2,123 | $200 | - | - | - |
$5,003
-
MMBtu
|
$(-2,880.0) | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $197 | $674 |
$115
2,871
kWh
|
$83
-
kW-mo/yr
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $271,828 | $776,504 |
$116,167
2,902,794
kWh
|
$130,745
-
kW-mo/yr
|
$10,636 |
$5,003
-
MMBtu
|
$1,908 | $2,370 | $5,000 | ||
TOTAL IMPLEMENTED | $269,210 | $773,324 |
$116,167
2,902,794
kWh
|
$130,745
-
kW-mo/yr
|
$10,636 |
$5,003
-
MMBtu
|
$1,760 | $(-100.0) | $5,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs