| Assessment Year | 1990 |
|---|---|
| Principal Product | PRINTED WIRING BOARDS |
| NAICS |
n/a
|
| SIC | 3672: Printed Circuit Boards |
| Sales Range | $10 M to 50M |
| # of Employees | 900 |
| Plant Area |
n/a
|
| Annual Production | 500
thousand feet
|
| Production Hrs. Annual | 7,200
hrs
|
| Location (State) | South Carolina |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,517,000 | 34,415,886 |
kWh
|
$0.044 |
| Natural Gas | $314,700 | 103,524 |
MMBtu
|
$3.04 |
| Fuel Oil #2 | $42,000 | 9,800 |
MMBtu
|
$4.29 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $80,659 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $55,976 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2163: Use minimum steam operating pressure | $46,500 | - | - |
$37,137
-
MMBtu
|
$9,363
-
MMBtu
|
|
| 02 | 2.2425: Use flue gases to heat process or service water | $11,598 | $10,600 | - |
$9,318
-
MMBtu
|
$2,280
-
MMBtu
|
|
| 03 | 2.6212: Turn off equipment during breaks, reduce operating time | $7,159 | - | - |
$5,718
-
MMBtu
|
$1,441
-
MMBtu
|
|
| 04 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,317 | $1,500 | - |
$1,863
-
MMBtu
|
$454
-
MMBtu
|
|
| 05 | 2.4239: Eliminate or reduce compressed air usage | $8,740 | $2,460 |
$8,740
198,710
kWh
|
- | - | |
| 06 | 2.4312: Improve lubrication practices | $4,345 | - |
$4,345
98,769
kWh
|
- | - | |
| TOTAL RECOMMENDED | $80,659 | $14,560 |
$13,085
297,479
kWh
|
$54,036
-
MMBtu
|
$13,538
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $55,976 | $1,500 | - |
$44,718
-
MMBtu
|
$11,258
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Fuel Oil #2 Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs